AUTUMN 2021
Sadly once again Covid -19 has prevented us from sending volunteers from the Uk to SHARE .
This has however not prevented huge progress being made at the site .
Work commenced on the school building removing tons of old bitumen, rubble , concrete slabs and rubbish from the existing roof , a mammoth task .
The walls were raised to an equal level and the corners strengthened before replacing the concrete roofing slabs . Following this the new second storey block work was completed and the building has now been covered for the winter months in order to keep it dry .
A huge water pit has been dug in order to meet fire safety regulations .
Fruit trees and blueberry bushes have been planted in the orchard .
In compliance with planning regulations preparatory work has begun at our adjacent site across the road from the main complex .
Thank you to everyone who has worked so hard this year and to all of you who continue to support us .
Summer 2020
Although sadly we were not able to have UK volunteers on-site last year we were able to accommodate several families with some disabled children in the completed guest house.This happened on two separate occasions. The families were absolutely delighted with the standard of accommodation and equipment. They had a wonderful recuperative holiday with yoga classes, birthday meals and sing-along evenings. As a thank, you several of the husbands and some of their local friends volunteered to continue the work on the garage block.Please pop over to the Gallery page to see some photos.
Volunteer Fortnight
Autumn 2019
Our autumn volunteer weeks saw the team using the newly completed “guest house” , “luxury” was the cry from the volunteers as they enjoyed hot showers, running water , flush toilets and a warm bed !
The house now has a fully equipped kitchen and dining area , with fridge freezer , oven , and everything the ladies who cook for us could wish for.
There are five bedrooms offering accommodation for up to twenty people .
The volunteers completed the insulation and timber cladding to the front elevation of the garage block which now has a second storey and new roof . It will eventually have storage downstairs for aid and equipment , a banya and upstairs five bedrooms with a shower and toilet .All the pipe work is now in place .
A concrete pad has been poured to the rear of the building ready for the installation of summer showers.
The main school building roof was cleared of all debris and the chimney stacks demolished . A large industrial tarpaulin has been secured in place to keep the building dry over the winter months .
Our next Volunteer Weeks
8th - 22nd September 2019
In September we have a team of six volunteers once more being led by Robert Whitemore going to the project.
Also traveling will be Joan Packard, who thanks to a private donor will be purchasing all the internal fittings and equipment necessary to complete this phase, eg, roller blinds, bedding , cutlery, bedside lockers right down to the basics such as loo brushes . She will buy as much as possible locally to support the Belarusian economy.
Work will also be starting on the renovation of the garage block to make it water tight and secure for storage .
We hope to be joined in this work by building apprentices from a local technical colleges.
Spring Volunteer Week
March 2019
Our Spring 2019 volunteer weeks saw a team of five going out to the project in March . They were delighted to escape the mosquitoes of last May , but found the weather very cold .
The team was led once again by our Project building manager Robert Whitemore and he was joined by Ger Byrne from Ireland , Chris Broome , Alan David and David Allsopp.
We had made an appeal to the links to help fund the materials for this final push to complete the construction work of the guest house and we are pleased to say that so far we have been well supported .
Photographs of their progress can be seen on our Gallery page .
September/October Volunteer Weeks
October 2018
Despite unseasonably cold , wet and windy weather the volunteers achieved a great deal .
Internal all the floor tiling was virtually completed , partition walls built for the shower cubicles, and externally the building insulated and battened ready for its final cladding.
To complete the building in we need to install suspended ceilings and LED panels
Install the toilets , sinks and showers.
Manufacture and install internal doors
Install a kitchen sink, gas hob and basic units
Pour a concrete belt around the exterior of the building
Build a small porch over the main entrance.
Once this is done we will be ready to hand the building over to the building inspector for it to be signed off ready to equip.
If you have any of the skills to help with the above please do get in touch . We hope to shortly have the dates for volunteer weeks in Spring 2019
Photo shows the plans for Phase 2 The old school building
AND there is always time for some relaxation . One of our volunteers Jo, and the lovely Belarusian ladies who translate and feed the volunteers so well about to enjoy time on the lake .
Project S.H.A.R.E host 3 children from local Parish
August 2018
The Project Share site hosted the children from the local Parish for 3 days.
They stayed in the school rooms, cleaned them, took some rubbish out and got involved in numerous other needed jobs, as well as having some fun, of course !
The communal sitting area/BBQ is the most popular place for everyone!
It is fantastic the site is also ready being used from time-to-time for youth day trips and summer day camps.
Want to get involved in this fantastic project that has gone from nothing to this in such a short time? Please inbox us. There is loads of different things you can do.
Absolutely stunning thank you everyone who has helped this project come so far
April 2018 Trip Update
Five volunteers in April achieved an enormous amount . The “Guest House” ( phase one) porch was demolished, the interior gutted, floors dug out and sand scree put down before pouring the new concrete floors throughout.
The wooden roof structure over the existing building and extension was finished , battened and felted ready for tiling. Drainage conduits were put in place for utilities .
In September we will complete the interior and start work on preparing the school building walls and flat roof ready to take the second storey
Art Exhibition
We held a very successful art exhibition in St Ives last month selling fourteen paintings and raising over £700 for S.H.A.R.E.
Father Vitali had arranged for us to have the art work of Belarusian children aged 8-15 years which had been entered into a regional competition in Belarus .
As the result of the wonderful reaction by the public to this exhibition we will be holding another one later this year.
Project S.H.A.R.E Support
We would like to thank the following Chernobyl Children's Lifeline Links for your continued support for Project S.H.A.R.E
St Ives
Ayrshire
N Wales
Nottingham
Middlesborough
Ashford and Romney
Wessex
Tamar
Pinxton
Wokingham
Newark
West Glamorgan
Plymouth
Bonsal
Sefton
Sherbourne & Yeovil
Havant & Waterlooville
If you are a Link of the charity, an external company or individual and you wish to support the project we would love to hear from you.
Our First Shipment of Aid
February 2018
Our first load of doors, toilets , shower trays and building supplies has been delivered from Cornwall to Stockton on Tees to Chernobyl Aid UK who are kindly including our items in their convoy going to Belarus later this month.